Production Line Industrialization · QT-2026-WC-02 · Standard 10-Week Program
Rename labels or descriptions. Built-in IDs (200, 400, 600) cannot be deleted.
Throughput scenarios and duplication analysis. Select the active scenario — this updates the station cards and the My Work view too.
| Station | 200/day | 400/day | 600/day | Bottleneck risk |
|---|
| Takt | OEE | Units/day | 34-day total | vs 2,800 | Status |
|---|---|---|---|---|---|
| 3 min | 100% | 160 | 5,440 | +2,640 | Comfortable |
| 3 min | 85% | 136 | 4,624 | +1,824 | Achievable |
| 4 min | 100% | 120 | 4,080 | +1,280 | Achievable |
| 4 min | 85% | 102 | 3,468 | +668 | Tight — monitor |
| 2 min | 85% | 204 | 6,936 | +4,136 | Comfortable (torque drivers) |
Drag bars to move · drag right edge to resize · click label to edit · changes sync to Tasks tab.
| Area | Owner | Notes |
|---|---|---|
| 3D model, crane, press, lifting table | Thomas | Primary engineering deliverables from sonnen |
| Testing specification document | Hunter | WC deliverable; Lukas provides EOL requirements |
| EOL setup requirements | Lukas Lenghoff | sonnen contact for EOL rig and test config |
| PFMEA cross-functional | HSE + battery team | Thomas to identify and schedule internally |
| Process flow, layout, WIs, PFMEA, control plan | WC | Core deliverables per QT-2026-WC-02 |
| Torque specs, bolt counts, reuse policy | Thomas | Required before WIs and torque tool orders |
| Capacity simulation (200/day vs 600/day) | WC | Requires measured cycle times from simulation visit |